6 March 2007
Progress Report March 2007
Construction of Lumière is progressing rapidly with almost 400 construction crew now on site.
The exterior glass 'curtain wall' is now installed to level 53.
Inside Lumière, interior walls have been gyprocked (cladded) to level 53, floor tiles or timber has been laid to level 34, kitchen and bathroom joinery is being installed to level 30 with benchtops now being installed below level 20.